Business

Latest MTCC Project Updates: Developments in 6 Islands

Maldives Transport and Contracting Company (MTCC) has announced that work on S. Hulhudhoo Harbour is well underway, with overall 23% project progress. Currently, dredging works for the project is ongoing. The project was awarded on 1 March 2020.

Work on Ha. Hoarafushi Football Ground Sub Base Preparation project is taking place, with an overall 61% project progress. Kerbstone laying, the casting of drainage gutter top, subbase fill levelling and compaction works are currently ongoing.

The construction of major roads for B. Eydhafushi is well underway, with overall 87% project progress. The asphalt work of the roads is now complete. Installation of a pump station and streetlights are now ongoing. The project was mobilized on 22nd April 2019.

The work on K. Maafushi Land Reclamation and Shore Protection project is being done, with an overall 78% project progress. Revetment works for the project is currently ongoing. The project was mobilized on 17th September 2019.

K. Maafushi Land Reclamation and Shore Protection project

K. Guraidhoo Land Reclamation and Shore Protection project is well underway, with an overall 22% project progress. Reclamation works for the project is currently ongoing, with 20% completion. The project was awarded on 27th August 2019.

Most recently, it was revealed that work on M. Veyvah Harbour is well underway, with an overall 39% project progress. The construction of a concrete wall and the installation of mooring rings are currently ongoing, with 39% and 20% completion respectively. The project was awarded on 27th August 2019.

Full details are available at the link below:

Subscribe
Notify of
guest
0 Comments
Most Voted
Newest Oldest
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x