Housing Development Corporation (HDC) has revealed that STO Hiya temporary Quarters at Hulhumale’ Phase 2 are reaching completion with the support of Beijing Urban Construction Group (BUCG) and Jausa Construction.
HDC has revealed that around 53% of the project has been completed, and it is expected to be completed by 18th May.
Construction of STO Hiya temporary quarter is currently underway in Phase II, Hulhumalè . Expected to be completed by 18 May 2020, these two blocks will shelter 1292 people.
we appreciate @BUCG & @JAUSA for their services & support in safeguarding the well being of our community pic.twitter.com/z5HerLrhlX
— HDC (@hdcmaldives) May 6, 2020
The two-block quarter will provide accommodation to 1292 expatriate workers living in congested living spaces. This project includes 6 buildings with 1 mess room and 1 toilet block.
HDC has appreciated the services and support BUCG and Jausa Construction has provided to the corporation in its mission to safeguard the community.